Wednesday, 28 November 2007
Roof ready for tiling
Wednesday, 21 November 2007
Roof Timbers
Sunday, 18 November 2007
The roof timbers are in place
The back wall is finished!
Friday, 9 November 2007
Bricks and Mortar


The Church Building Project Team are being bombarded with decisions such as colour schemes for window frames and toilet cubicles, and where we want plug sockets and light switches. There is a lot of information and at times we struggle with the responsibility of knowing whatever we decide, the church has to live with it for years to come – please pray for us.
Friday, 2 November 2007
Internal walls


The Financial Situation
The past month has been a
miraculous time at St John’s. In the last update at the beginning of October the finances stated that we had raised £260,645. As we stand today we have now raised over £350,000. This means that over £90,000 has been received within the last month – praise the Lord! And thank you to you if you have given generously in the last few weeks.
At the moment we will run out of available cash to pay the builders at the beginning of February.
The past month has been a
miraculous time at St John’s. In the last update at the beginning of October the finances stated that we had raised £260,645. As we stand today we have now raised over £350,000. This means that over £90,000 has been received within the last month – praise the Lord! And thank you to you if you have given generously in the last few weeks.
At the moment we will run out of available cash to pay the builders at the beginning of February.