Friday 25 January 2008

8 weeks to go





This shows the size of the new entrance hall the scaffolding has now been removed and the back wall plastered. A lot happens here in a week. By the end of Friday most of the glass for the windows and doors will be installed.













The plasterers moved in on Monday, they have made a vast difference in a short space of time . Here is the corridor from the main foyer, fully plastered and in the foreground can be seen the window fitters installing the glass to the doors.







The floor to the classrooms for the play group are finished and the boarding of the walls is well under way. This side of the building should be plastered fully by the end of next week.

9 Weeks to go






This is the view into the corridor from the main foyer, here we can see the scree floor being laid.




























Work is progressing at a fair rate and the door and window frames are now being installed.

Saturday 12 January 2008

A new year but the work continues








Well the roof is nearly finished and the scaffolding has come down so the church is now starting to look finished from the outside. You can now feel how big the new building will be when it is completed.








Whilst the work outside is nearly completed the work inside still continues at a similar pace.



The first fix for the electrics, plumbing and carpentry is nearly finished and the plasterboarding of the worship hall ceiling is well over half done.












Lets not forget what is happening in the other parts of the building, here is the start of the scree floor being laid in the classrooms of the family centre.












Here we can see the finished floor and the piping of the soon to be gents toilet.