Saturday 13 October 2007

Two weeks ahead of schedule!





The builders are currently two week’s ahead of schedule! Have you ever heard of a building project being ahead of schedule? We give thanks to God for the good weather that has enabled the crucial stage of digging and filling the foundations to progress easily, for the steady building progress without complications, and for Ralph May’s positive attitude and relationship with everyone from the church.

Current position: The foundations have been completed, and the steel frame for worship space and entrance area is in place - it looks like a massive frame tent at the moment. The frame only covers half of the final building size as the children's classrooms, corridor, meeting rooms and toilet don't require a steel frame.
Next steps:
The concrete floor and drainage services will be laid week beginning 14th October.
Week beginning 28th October the outside brick and block work will start to be built.