Thursday 27 December 2007

A Roof at Last


Well the building is starting to come together, we now have a nearly finished roof. The inside is also changing, the first fix for the electrics has taken place and a brave bunch of people from St John's installed the cabling for the PA system and Data cables.
The month of January is going to be very busy, with the roof being completed, the windows being installed, the floor being laid in the family center and the plaster boarding of the roof in the worship area.

No comments: